Home
Edit Profile

Weekly Report: 11/03/2025 - 11/09/2025

Total hours: 262.2 hrs
Total payment: $6137.91
ARMANDO SANCHEZ
SEICO SERVICES
43:01 Tasks: 6
Payment: $1247.58
Adjust Time
Hourly Rate: $29.00
Project: CROSSROADS DAYCARE
Total hours: 1.00 hrs | Total payment: $29.00
  • 101 TIME FROM JOB TO JOB
    $29.00
Project: HARMONY BANK
Total hours: 42.02 hrs | Total payment: $1218.58
  • 13 EXTERIOR FRAMING
    $725.58
  • 14 INTERIOR FRAMING
    $246.50
  • 21 SHEATHING
    $246.50
ISRAEL BERMUDEZ
SEICO SERVICES
46:09 Tasks: 9
Payment: $1338.35
Adjust Time
Hourly Rate: $29.00
Project: OFFICE
Total hours: 0.97 hrs | Total payment: $28.13
  • 101 TIME FROM JOB TO JOB
    $28.13
Project: PENIKAM ADDITION
Total hours: 37.18 hrs | Total payment: $1078.22
  • 13 EXTERIOR FRAMING
    $295.22
  • 14 INTERIOR FRAMING
    $580.00
  • 71 BLOCKING
    $203.00
Project: SUNSHINE KIDS MCKINNEY
Total hours: 8.00 hrs | Total payment: $232.00
  • 101 TIME FROM JOB TO JOB
    $58.00
  • 14 INTERIOR FRAMING
    $174.00
JONATHAN VARGAS
SEICO SERVICES
47:31 Tasks: 8
Payment: $1235.52
Adjust Time
Hourly Rate: $26.00
Project: ENVOY
Total hours: 3.75 hrs | Total payment: $97.50
  • 60 CEILING TILE
    $97.50
Project: LOFTIN
Total hours: 31.75 hrs | Total payment: $825.50
  • 20 DRYWALL
    $679.12
  • 40 INSULATION
    $146.38
Project: PENIKAM ADDITION
Total hours: 12.01 hrs | Total payment: $312.26
  • 13 EXTERIOR FRAMING
    $212.68
  • 14 INTERIOR FRAMING
    $99.58
JORGE SALDIVAR
SEICO SERVICES
45:59 Tasks: 8
Payment: $1241.46
Adjust Time
Hourly Rate: $27.00
Project: PENIKAM ADDITION
Total hours: 37.98 hrs | Total payment: $1025.46
  • 13 EXTERIOR FRAMING
    $593.46
  • 14 INTERIOR FRAMING
    $243.00
  • 71 BLOCKING
    $189.00
Project: SUNSHINE KIDS MCKINNEY
Total hours: 8.00 hrs | Total payment: $216.00
  • 101 TIME FROM JOB TO JOB
    $54.00
  • 14 INTERIOR FRAMING
    $162.00
LUIS NAVA
Q&V LABOR
09:30 Tasks: 1
Payment: $0.00
Adjust Time
Hourly Rate: $0.00
Project: LOFTIN
Total hours: 9.50 hrs | Total payment: $0.00
  • 20 DRYWALL
    $0.00
MARIO DUARTE
Q&V LABOR
27:02 Tasks: 5
Payment: $0.00
Adjust Time
Hourly Rate: $0.00
Project: ENVOY
Total hours: 2.78 hrs | Total payment: $0.00
  • 60 CEILING TILE
    $0.00
Project: LOFTIN
Total hours: 12.25 hrs | Total payment: $0.00
  • 20 DRYWALL
    $0.00
Project: PENIKAM ADDITION
Total hours: 12.00 hrs | Total payment: $0.00
  • 13 EXTERIOR FRAMING
    $0.00
  • 14 INTERIOR FRAMING
    $0.00
RUBEN CORONA
Q&V LABOR
43:00 Tasks: 5
Payment: $1075.00
Adjust Time
Hourly Rate: $25.00
Project: HARMONY BANK
Total hours: 43.00 hrs | Total payment: $1075.00
  • 13 EXTERIOR FRAMING
    $650.00
  • 14 INTERIOR FRAMING
    $212.50
  • 21 SHEATHING
    $212.50
Employee Company Total Time Payment ($) Actions
ARMANDO SANCHEZ
6 tasks
SEICO SERVICES
43:01
43.02 hours
$1247.58 Adjust Time
Hourly Rate: $29.00
Project: CROSSROADS DAYCARE
Total: 1.00 hrs $29.00
Task Hours Payment
101 TIME FROM JOB TO JOB 1.00 $29.00
Project: HARMONY BANK
Total: 42.02 hrs $1218.58
Task Hours Payment
13 EXTERIOR FRAMING 25.02 $725.58
14 INTERIOR FRAMING 8.50 $246.50
21 SHEATHING 8.50 $246.50
ISRAEL BERMUDEZ
9 tasks
SEICO SERVICES
46:09
46.15 hours
$1338.35 Adjust Time
Hourly Rate: $29.00
Project: OFFICE
Total: 0.97 hrs $28.13
Task Hours Payment
101 TIME FROM JOB TO JOB 0.97 $28.13
Project: PENIKAM ADDITION
Total: 37.18 hrs $1078.22
Task Hours Payment
13 EXTERIOR FRAMING 10.18 $295.22
14 INTERIOR FRAMING 20.00 $580.00
71 BLOCKING 7.00 $203.00
Project: SUNSHINE KIDS MCKINNEY
Total: 8.00 hrs $232.00
Task Hours Payment
101 TIME FROM JOB TO JOB 2.00 $58.00
14 INTERIOR FRAMING 6.00 $174.00
JONATHAN VARGAS
8 tasks
SEICO SERVICES
47:31
47.52 hours
$1235.52 Adjust Time
Hourly Rate: $26.00
Project: ENVOY
Total: 3.75 hrs $97.50
Task Hours Payment
60 CEILING TILE 3.75 $97.50
Project: LOFTIN
Total: 31.75 hrs $825.50
Task Hours Payment
20 DRYWALL 26.12 $679.12
40 INSULATION 5.63 $146.38
Project: PENIKAM ADDITION
Total: 12.01 hrs $312.26
Task Hours Payment
13 EXTERIOR FRAMING 8.18 $212.68
14 INTERIOR FRAMING 3.83 $99.58
JORGE SALDIVAR
8 tasks
SEICO SERVICES
45:59
45.98 hours
$1241.46 Adjust Time
Hourly Rate: $27.00
Project: PENIKAM ADDITION
Total: 37.98 hrs $1025.46
Task Hours Payment
13 EXTERIOR FRAMING 21.98 $593.46
14 INTERIOR FRAMING 9.00 $243.00
71 BLOCKING 7.00 $189.00
Project: SUNSHINE KIDS MCKINNEY
Total: 8.00 hrs $216.00
Task Hours Payment
101 TIME FROM JOB TO JOB 2.00 $54.00
14 INTERIOR FRAMING 6.00 $162.00
LUIS NAVA
1 tasks
Q&V LABOR
09:30
9.50 hours
$0.00 Adjust Time
Hourly Rate: $0.00
Project: LOFTIN
Total: 9.50 hrs $0.00
Task Hours Payment
20 DRYWALL 9.50 $0.00
MARIO DUARTE
5 tasks
Q&V LABOR
27:02
27.03 hours
$0.00 Adjust Time
Hourly Rate: $0.00
Project: ENVOY
Total: 2.78 hrs $0.00
Task Hours Payment
60 CEILING TILE 2.78 $0.00
Project: LOFTIN
Total: 12.25 hrs $0.00
Task Hours Payment
20 DRYWALL 12.25 $0.00
Project: PENIKAM ADDITION
Total: 12.00 hrs $0.00
Task Hours Payment
13 EXTERIOR FRAMING 8.00 $0.00
14 INTERIOR FRAMING 4.00 $0.00
RUBEN CORONA
5 tasks
Q&V LABOR
43:00
43.00 hours
$1075.00 Adjust Time
Hourly Rate: $25.00
Project: HARMONY BANK
Total: 43.00 hrs $1075.00
Task Hours Payment
13 EXTERIOR FRAMING 26.00 $650.00
14 INTERIOR FRAMING 8.50 $212.50
21 SHEATHING 8.50 $212.50

Showing 1 to 7 of 7 results